Skip to content

Behind the model

How the manufacturing model works

Every number in the model is worked out from your inputs; nothing is hidden. Below is each formula, paired with a worked example from the default 10,00,000-unit-a-year plant. Change any input in the model and the same formulas apply.

Output and capacity

The plant has a rated yearly capacity; what it actually makes in a year is capacity × that year’s utilisation (see the ramp-up below).

Rated capacity

annual capacity (units / yr)

10,00,000 units/yr

Units produced (year y)

capacity × utilisation(y)

stabilised: 8,00,000 units (80% util)

Yearly output, once busy

capacity × stabilised utilisation%

8,00,000 units/yr

Set-up cost (CapEx)

Land (plus stamp duty), building, machinery, utilities and other one-time costs, then a buffer for surprises (contingency) and interest during construction (IDC). Set-up cost per unit of capacity is worked out, never assumed.

Stamp duty on land

land × 6% (registration, by state 5–7%)

₹12 L

Base build cost

land + stamp duty + building + machinery + utilities + Σ line items

₹34.9 Cr

Buffer for surprises (contingency)

base × 5%

₹1.75 Cr

Subtotal (with buffer)

base + contingency

₹36.7 Cr

Interest during construction (IDC)

total × debt% × interest% × (months ÷ 12) × ½

12 mo → ₹1.1 Cr

Total project cost

sub-total + IDC

₹37.8 Cr

Set-up cost per unit of capacity

total project cost ÷ annual capacity

₹378 / unit

Running costs (OpEx)

Variable costs (raw materials, power) move with units made; fixed costs (labour, maintenance, other) are yearly and rise each year. Power cost is worked out from use × tariff, never typed in.

Raw materials (variable)

units × RM cost/unit × (1 + opexEsc)^(yr−1)

stabilised: ₹30.9 Cr/yr

Power cost per unit

kWh/unit × tariff = 3 × ₹8.5

₹25.50 / unit

Labour and power

annual labour + units × power cost/unit, escalated

stabilised: ₹7.49 Cr/yr

Maintenance

(base + contingency, pre-IDC) × 2.5% / yr

stabilised: ₹1.01 Cr/yr

Other fixed costs

other fixed annual, escalated

stabilised: ₹3.31 Cr/yr

Working-capital interest

see Working capital below: an opex line

stabilised: ₹85.6 L/yr

Total running costs

raw materials + labour & power + maintenance + other fixed + WC interest

stabilised: ₹43.5 Cr/yr

Yearly cost rise

base × (1 + 5%)^(yr−1)

5% / yr

Working capital: the standard bank method

Cash locked in raw material, work in progress, finished stock and unpaid customer invoices. Indian banks size it as days of sales, fund (1 − margin) through a cash-credit limit, and expect you to fund the margin yourself.

Amount needed (year y)

revenue(y) × cycle days ÷ 365 = revenue × 75/365

stabilised: ₹10.9 Cr

Bank cash-credit limit

requirement × (1 − 25% margin)

₹8.16 Cr

Your margin

requirement × 25%: funded from equity

₹2.72 Cr

Cash-credit interest (a running cost)

bank-funded share × 10.5%: reduces EBITDA

stabilised: ₹85.6 L/yr

Change in working capital (cash used)

requirement(y) − requirement(y−1); full Δ hits project cash flow, the margin share hits equity

year 1: ₹6.16 Cr

Returned at the end

final-year requirement returns as cash in the last year

₹16.9 Cr

Revenue, ramp-up and phasing

Revenue is units made × price, with the price rising each year. Utilisation climbs in a straight line from the year-1 level to a steady level; a phased build adds capacity one phase at a time.

Revenue (year y)

units(y) × price/unit × (1 + priceEsc)^(yr−1)

year 1: ₹30 Cr → stabilised: ₹52.9 Cr

Yearly price rise

price × (1 + 5%)^(yr−1)

5% / yr

Utilisation ramp-up (straight line)

start + (stabilised − start) × (age−1) ÷ (ramp yrs − 1)

50% → 80% over 3 yrs

Phased build

each phase commissions on its own year and ramps from scratch

leave blank for an all-at-once build

Loan, repayment holiday, tax and depreciation

A term loan with interest only during the repayment holiday (moratorium) while the plant ramps up, then principal repaid over the rest of the loan term. Straight-line depreciation on everything except land; tax with losses carried forward.

Loan and your money

debt = total cost × debt% ; equity = remainder

₹22.7 Cr debt · ₹15.1 Cr equity

Repayment holiday (moratorium)

interest-only for the first N years, then amortise

2 yr grace, 8 yr tenor

Equal-principal repayment

debt ÷ (tenor − moratorium) each amortising year

₹3.78 Cr / yr over 6 yrs

Fixed EMI option

debt × r ÷ (1 − (1+r)^−(tenor−moratorium))

level-payment alternative

Loan interest

outstanding balance × interest rate

year 1: ₹2.27 Cr (interest-only)

Depreciable base (land excluded)

total project cost − land − stamp duty

₹35.6 Cr

Depreciation (straight-line)

depreciable base ÷ 15 yrs

₹2.38 Cr / yr

Tax (losses carried forward)

max(0, PBT − losses) × 25% ; losses carry forward

shelters early-year losses

Capital subsidy: state and central schemes

Many state industrial policies subsidise 10–25% of eligible fixed investment (not counting land), paid after production starts. The model counts it as one-time cash in the first operating year; it never changes the loan size or the depreciation. Whether you qualify is decided by the department running the scheme.

Eligible investment (not counting land)

building + machinery + utilities + line items

₹32.8 Cr

Capital subsidy

eligible investment × 0%

₹0 (off by default)

Timing

received in the first operating year (post-commissioning disbursal)

boosts year-1 cash flow, payback and IRR

Returns and loan cover

Cash flows before any loan give the project return; cash flows to you give the return on your money. The project return uses tax without the loan-interest saving, so it doesn’t depend on how you borrow. A longer build pushes back the first sales and deepens the early dip in cash.

Operating profit (EBITDA)

revenue − total OpEx (incl. WC interest)

stabilised: ₹9.39 Cr (18% margin)

Project cash flow

EBITDA − project tax − CapEx − ΔWC (+ subsidy yr 1, + WC release at horizon)

Project IRR 12.6%

Cash to you

PAT + depreciation − principal − equity-funded CapEx − margin share of ΔWC

Equity IRR 19.7%

Build delay

first revenue deferred by ⌈months ÷ 12⌉ − 1 extra years

no extra lead year

Value above your hurdle (NPV)

Σ unlevered FCF ÷ (1 + discount)^t

@ 12% = ₹1.6 Cr

Payback

year cumulative unlevered cash flow first turns positive

7.2 yr

Loan cover (DSCR)

CFADS ÷ debt service ; CFADS = EBITDA − tax (amortising years only)

min 1.43× · avg 1.80×

Loan-life cover (LLCR)

PV(CFADS over loan life) ÷ debt

1.70×

Money back per ₹1 (equity multiple)

Σ equity cash returned ÷ equity invested

4.60×

Break-even utilisation

stabilised utilisation at which project NPV = 0

78%

Per unit, in a settled year

What each unit earns and costs once the plant is busy.

Revenue per unit

stabilised revenue ÷ stabilised units

₹662

Running cost per unit

stabilised OpEx ÷ stabilised units

₹544

Contribution per unit

(revenue − variable cost) ÷ stabilised units

₹248

Set-up cost per unit of capacity

total project cost ÷ annual capacity

₹378

Energy and carbon

What the plant uses and emits once it is busy.

Energy

annual units × power (kWh/unit) ÷ 1000

2,400 MWh/yr

Carbon

energy (kWh) × grid emission factor ÷ 1000

1,704 tCO₂/yr

Carbon per unit

power (kWh/unit) × grid emission factor

2.13 kgCO₂/unit

Contribution margin

(price − RM − variable power) ÷ price

37%

These are planning estimates you can check line by line, not a quote. The typical Indian figures are assumptions from public sources, not ClarWorks data, and every one can be changed in the model. Open the model →

Advisory · Project report and bank finance

Taking this to a bank? Get the numbers checked first.

We go through your model with you: the assumptions, the costs, the loan structure and the risks. If you need one, we write the detailed project report your bank will appraise. The loan decision is always the bank’s; our job is to make your case clear and complete.

  • Free 30-minute first call, online
  • Paid work quoted before it starts
  • Direct with the person doing the work

Replies within 24 hours. Prefer WhatsApp? Message us

Funded and getting ready to open? We also build the software a business runs on: orders, billing, stock, and WhatsApp ordering. Fixed scope, fixed price, in writing before work starts.